We've completed the general assembly of the components and assemblies of the first of two ACV-17R cement trucks on a KAMAZ chassis. The cement tank, pipelines, and fine filter have been installed. We're connecting the compressor unit to the pipeline and checking that everything is in place.

There's still a lot of work ahead. After checking the connections, we'll dismantle all the equipment and send it off for painting so we can finally assemble the cement truck and conduct testing.